Reconstruction of the blind area of ​​the country house. Part 3.

click fraud protection

Continuing it and it report, we present the final report on the work carried out by our company in one of the holiday villages Pyatnitskoe highway in the Moscow region.

The task: Perform reconstruction of the blind area, construction of houses adjoining the drainage system with drain well in the interim storage.

Progress of works: Thus, the final stage of the work was the reconstruction of the blind area and the adjoining circular arrangement drainage with tap water table in intermediate well and discharged into obscheposelkovy drainage. In the first place it was to dismantle the old blind area and developed a new trench, as well as for the installation of drainage pipe:

After development of the trench, it was placed in the tube as follows: the bottom of the trench is laid geotextile waking up one layer of gravel, in which the drainage pipe is laid. Then, a height of about 5-10 cm above the upper generatrix of the tube, and also laid gravel geotextile fabric ends are summarized together. To thereby obtain the drainage layer. In the photo below, you can see it:

instagram viewer

The ultimate drainage pipe is retracted into the intermediate storage well:

After the drainage pipe has been laid, the bedding was made under the ground level of the base of the blind area, then it is time for the formation of cushion otmostku. It achieved this two layers - a layer of gravel, about 10-15 cm and a top layer of sand with a thickness of about 10 cm. In the process of forming pillows, both layers are parallel and tamp thoroughly spilled water:

After preparing the cushion under the blind area, it was undeveloped formwork. At arrangement of the formwork should pay attention to the following: the formwork must be mounted wooden dividers, every 1.5-2 m. Near the base is laid insulation, which prevents the "sticking" of the blind area to the cap and ensure its freedom of movement relative to the base off-season. Example of arrangement under the blind area formwork you can see in the photo below:

Upon completion of all preparatory work is the time to fill immediately. There is nothing special to describe, as they say: take more - throw farther. The only thing you need to pay attention - this is not to forget to lay reinforcing mesh and atone smoothly, providing the desired slope, which is formed by another arrangement step pillows. What we have as a result of filling the blind area you can see in the photo below:

More detailed information on progress of the works can be found in our photo gallery. Total time of execution of works on arrangement of blind area was 5 days.

New items for the holiday of a wooden house

New items for the holiday of a wooden house

For a garden plot in the Russian wooden house remains the most popular option. Detached bungalow,...

Read More

LED lights of the village and its area

LED lights of the village and its area

Once in 2016. along our sites set electric poles, transformers (substations) and connected electr...

Read More

Artificial stone without tree bark forms

Artificial stone without tree bark forms

How to make your own artificial stone beneath the bark? See one idea stones of plaster under the ...

Read More

Instagram story viewer