I continue to build the walls of the timber. I do have time before the snow?
As is clear from previous articleI write this stage of the construction of the memory on the basis of the surviving photographs. In a previous article I showed the process and speed of erection of buildings baths of planed timber. In this article - continuation of the process.
As you can see, picking up to this date I have already started laying 9th crown log. To the right it can be seen that at first I did cutout guide the door of the box, but to save time, later abandoned the process.
This period of the fall was surprisingly warm and almost no rain. If frequent rains, I could not even pass on their construction, as the road was simply black earth, field. But until then, it was not the day that I could not drive his minivan. So far, everything went more or less according to the conceived plan.
From permanent formwork when casting the plate washing remained flat slate. I instructed my assistant to impose from the outside of the span between the piles under the wall and sprinkle the clay to fix. But he overdid it. Later it had to cut part of the clay and move.
After October 1, I came down with a cold. I did not expect this from him. It knocked me out of the process for a few days. Works could continue only to the 12 October. And then there is a period when frequent rains, do not let us work.
From 01 to 12 October, I was able to put only be seen 2 crown and third I started. The photograph shows that made the forest: timber structure with two sides having a projection of about 0.5 m. Put the tabs on the two boards 150h50mm and increased their stand in the middle. Assistant began caulk bath hammer hanging tow into the seams of wooden "spatula" and hammer. This work took him nearly all the time until the end of construction.
As he wrote in previous articles, I went to the construction site during the week, in advance otprashivayas to work 3-4 hours in the day. It was getting dark quite early, work was only 2-3 hours.
The time it took to move to the construction site 35 km from the city. Still I had to dress up and dine. The food was unpretentious: buy canned food (meat and fish), bread, he took water and tea in a thermos. Work always begins with such a dinner with an assistant, who also was cheesy in this regard.
Progress is, but slowly. It can be seen that the timber already partially blue from the fungus as rains. Then he had to these places bleach bleach wood. masonry looks curve to the left. No, it is not filled up, the length of each segment of the timber are of different lengths. It's not terrible - after opening under the stove sawed vertically.
13 laid wreaths. The structure acquires a more or less harmonious appearance and shape. The front part of the log at this stage zakonopachena.
I proceeded to 14th crown. According to the project planned 17 crowns. Again there was a pause in the work. Not every night could go to the construction site. Prevented the rains, the work. Wife has already started grumbling - my absence in the evenings she obviously did not like. As the prospect of my self-construction. Many girls and women in this respect are more conservative, and their opinion: it is necessary to hire employees - they are built.
After October 18 came another pause in the construction of up to 27 th of October. And I could not believe I have time at a comfortable weather and air temperature to finish the frame and the roof?
About the next phase of construction - read the article:
The construction of terraces and roof rafters square log baths
Read from the beginning: Why I decided to build a house?