Useful content

Cottages for 6 × 6: their own hands, with a minimum budget

click fraud protection

Bowers acquire different - receive an inheritance, buying plots with a house and rework or finish by yourself or buy land is almost in the open field and begin development of virgin lands. Just such a process was puzzled by one of our craftsmen, who decided to join the country life. And as the most effective way to save money - do it with your hands, just as he did, start small - with country house "for the first time."

Content

  • Suburban house 6 × 6 with integrated terrace 4 × 3:
  • project;
  • foundation;
  • water supply;
  • box;
  • inner workings.

Suburban house 6 × 6 with integrated terrace 4 × 3

Gonzik1 (User FORUMHOUSE):
In the last year bought land in the field (such as the new holiday village). The pillars have been installed, the electricity conducted to the site (on the paperwork it took about two months), finally put the shield on a pillar with a counter, a gun and socket. This year, having saved up some money, began construction. I decided to do everything with your hands, because it is cheaper and more reliable.
instagram viewer

Project

house project for the first time created a craftsman in the winter, he conceived - it is the first unit to which he later joined up another, combining both parts into a coherent structure. With the special program a drawing made that allowed to accurately count the number of materials required.

Foundation

Since the house is a lightweight, on frame technology and one floor, Gonzik1 I opted for special pier foundation of concrete blocks (20 × 20 × 40 cm). Also influenced his choice of a low groundwater level (GWL) and the excellent condition of these bases under the neighboring buildings. Depending on the level used for one or two blocks of the pole - shot topsoil, sand slipped cushion stacking blocks. The plane sustained by a gidrourovnya. By craftsmen he said he appreciated this simple tool - and cheap, and accuracy is excellent. Columns covered with roofing material for waterproofing. With the help of family foundations he was ready in three days.

Water supply

Central water supply in the field take nowhere, so the problem of water supply - a private affair of each summer resident. Our craftsman originally planned to drill a well. Test drilling for thirty six meters turned out unsuccessful - instead of water went tight black clay. Drillers reported that only help borehole meter ninety, sounded exorbitant price. Gonzik1 porasstraivalsya presenting scale of the problem and decided to dig a well, as shown by the foreseeable future - the right decision. Three days, ten rings - a column of water a half ring is restored and a half hours.

Box

Tying bilayer - across the bottom board 100 × 50 mm, on top - 100 × 40 mm, impregnated ognebiozaschitoy, strapping elements joined together by nails (100 and 120 mm). Piping laid over roofing material and fixed to the posts with anchors.

All stud frame also collected from the board 100 × 40 mm on the nails, the walls raised directly on the site, using temporary jib. On the ground, we collected only strong point, after lifting it to the roof. At this stage it took another four days.

Mount the rafters, wind board, pulled the windshield, over kontrobreshetku and lathing. As a roofing craftsman chose our metal tiles.

Gonzik1:
Read that no matter which side of the stacked sheets, usually placed from left to right. It turned out there, tiles laid from right to left, or else the next sheet will have to start under the previous one, which is very inconvenient, especially when installing alone. The weather was not very good, drizzling rain was the wind moved across the roof like a cat trying to grab their feet in the crate. However, all twelve sheets of tiles (115h350 cm) got put in half a day.

After the shingles got his hands to the ground, because of which were not fully laid joists overlap. Gonzik1 Area used 50h50h4 mm, the compound of the metal strip 40x4 mm plus the length of self-insulated wire (SIP).

Next, shut down the entire structure a protective membrane, put the door, lay a floor board on the terrace began to skin facade imitation timber. Cashing immediately treated with protective impregnation. While working craftsman has made adjustments to the project - he took the third window and the light will be more attractive and the view from the window.

inner workings

With the end of the holiday as much as possible the process of building slowed as free weekend dropped every week, but continued. He graduated from the floor - the rough on logs from the GSP, on top of the waterproof membrane between joists slabs of stone wool, lath, and it again OSB. As topcoat assumed linoleum. Also the house has got another window.

Has got into the house electricity, insulate the perimeter of stone wool over the vapor barrier and lining as the lining.

Finish process continued using the same algorithm, contrasting trim on the window openings home decoration added. All internal walls will be sewn lining.

The house is scheduled for a seasonal residence, as the heaters Gonzik1 prefers autonomous heaters.

Gonzik1:
The furnace is not planned, the house seasonal residence - spring, summer, autumn. I plan to hang the electric convector heater, I have electricity there is no problem, three phase, a new substation of 15 kW per site.

For all interested craftsman put the calculation of materials (all used the board to 6 meters long):

  • foundation blocks 200 × 200 × 400 mm, 30 pieces;
  • board 50x100 mm, 8 pieces (for the lower layer of strapping);
  • board 40 × 100 mm, 96 pieces - in the residue of about 8 pieces;
  • board 25 × 10 mm, 128 pieces - approximately at residue 12 pieces;
  • timber 100 × 100 mm 3;
  • rake 25 × 50 mm, 15 pieces;
  • imitation lumber 18,5 × 146, 100 pieces - approximately at residue 15 pieces;
  • insulation, rockwool 1200 × 600 × 100 mm, 28 packages (6 plates) - remained packing;
  • waterproof membrane of 1.6 m width, 60 m ² on a roll, the roll 3;
  • steam, 1.6 m width, 60 m ² on a roll, 3 roll - in the residue of about 0.5 of the roll;
  • SIR March 2500 × 1200 × 9 mm, 15 pieces (roughing and finishing flooring) - a residue of approximately 1.5 plates;
  • metal 350 × 115 cm, 12 sheets;
  • lining 12.5 × 96 cm, 370 pcs (10 packages) - not the fact that will be enough, in part used on the toilet binder, and the walls are not finished;
  • Wooden window 1000 × 1000 mm, 3;
  • Input steel 2050 × 900 mm, 1 unit;
  • protective treatment for wood, 10 liters - a remainder of 3 liters, but the house is covered with only one layer.

Given the self-build and furnish estimates turned out quite a budget.

  • Foundation - 2500 rubles.
  • Board on frame, windscreen, steam, imitation lumber (exterior trim), lining (interior), insulation, and so on. D. - 110000 rubles.
  • Metal - 20,000 rubles.
  • Door - 13 200 rubles.
  • Windows - 4 200 rubles = x 3 12600 rubles.
  • Forwarding SIP home - 3000 rubles (by cable).
  • Impregnation - 3600 rubles.

Electrician still going to plant at home, I think, I put thousands of 8-10. The cost of nails, screws, staples and the like. D., And m. P. I do not bring, because I do not remember how much that purchase. Total: about 165,000 rubles.

For one brief, but fruitful holiday - finished with the electrician, finished interior trim paneling and painting, he made a set on the kitchen completed the terrace. The terrace spread a board 100 × 40 mm, taking planed, electroplane processed after impregnation plated in two layers. Over the past winter, everything is in place, did not lead anything, no rassohlos and not twisted. The plans for the craftsmen to finish the second unit, but this attempt at writing at the height - a great family-friendly lodge.

Trace for further accomplishments craftsman can his themeOf ready-cost alternatives - in the material of the houses of the tongue and about modular home. In the video - domokomplekta about the budget.

Subscribe to the channel and put the "Like" so as not to miss the next release!

Do not agree with the author, or find a mistake in the article - write about it in the comments!

Succinic acid - a natural growth stimulant for plants

Succinic acid - a natural growth stimulant for plants

The result of usingSuccinic acid stimulates growth and flowering indoor and garden plants. The sp...

Read More

How to keep the cabbage collected as long as possible ✔

How to keep the cabbage collected as long as possible ✔

Cabbage - this is one of the main elements of the diet of most people in Russia. However, often d...

Read More

Why all the roots of the orchid should be in the pot, rather than the top crust

Why all the roots of the orchid should be in the pot, rather than the top crust

unhealthy situationHello!Recently, I took seriously the cultivation of Phalaenopsis orchids. And ...

Read More

Instagram story viewer