Paving on the blind area
Here is another photo report on the work of laying the paving stones on the blind area around the house (the previous reports here, here and here).
The task: perform work on laying the pavers in the blind area around the house.
Progress of works: To begin with, the customer selected and imported stone blocks. The choice fell on a stone blocks "Old Town" of yellow and red. We must say no to the easy pitching, given that without first laying pattern can not do. In the photo below brought pavers "Old Town":
As noted above, the first thing that has been done - fixings was previously laid on the blind area for pattern matching with the client:
Upon completion of the computation of paving stones and obtaining approvals, work began on laying the pavers in the blind area. Paving performed on the sand-cement mixture at a ratio of 5: 1, i.e. 5 parts sand to 1 part cement. In this controlled slopes pavers, as an aside "from home", and in the direction of catchment wells:
In parallel with the paving executed installation of curbs and storm sewer line, which we describe in the next press release. Well, the result of work on the laying of pavers "Old Town" in the blind area around the house, after the "sweeping" of seams, you can see in the photo below:
Please note that the paving on otomstku - this is only part of the service improvement of suburban areas, which are rendered by our company. Along with this, we can make arrangement of suburban tracks by laying paving stones or paving slabs, as well as to provide a device of the underground and the linear section of the drainage. Contact, will be glad to see you among our customers!
More detailed information on progress of the works can be found in our photo gallery. The total time of work on the laying of pavers "Old Town" in the blind area around the house was 7 days.