Useful content

Overhaul of the holiday home. Part 3.

click fraud protection

Here is another review of the work we do on the overhaul of a country holiday home in the Mytishchi district, Moscow region (previous reports here and here).

The task: to carry out interior finishing rooms on the second floor of a wooden country house, including:

- dismantling the existing frame partitions;
- wall insulation slab insulation with vapor sealing arrangement;
- lining the walls of plasterboard, their putty and painting;
- finishing decorative boxes chimney;
- reconstruction of engineering systems (such as electricity, water, wastewater) by their complete replacement;
- finishing bathrooms, installing sanitary ware;
- installation of switches, sockets, lighting fixtures;
- leveling the floor, laying flooring.

Progress of works: As in the previous report, the first thing was to dismantle the old lining (where it was), and the interior walls. The photo below shows the premises, after the dismantling:

Upon completion of the dismantling were equipped engineering systems, namely, laid water system second floor suburban house from polypropylene pipes, wiring is formed through the rooms are equipped with ventilating channels.

instagram viewer

Then warming the outer perimeter of the house was carried out on the walls, construction of a metal frame assembly, primer, putty plasterboard. The problem was that in order to save, the customer had decided to maintain the maximum area existing plating (drywall), i.e. new design had to be put only in some places, stykuya and adjusting them for longer existing ones. Furthermore, at the stage of spackling, painting, had to "withdraw" the plane of new and existing structures in order to ensure the future integrity of the wall. In the photo below you can see the steps of the above finishing works:

After installation, patching, painting drywall, it is the turn of laying a floor covering - bamboo board as well as in the bathroom plumbing installation, the installation of interior doors, fittings and cashing. The result of these studies is shown in the photo below:

As in the previous photo report, the final stage of interior decoration rooms on the second floor of a country house was the installation of sockets, switches, lighting fixtures. More clearly with the result you can see by viewing the following video of the executed works on furnish rooms on the second floor of a wooden country house:

More detailed information on progress of the works can be found in our photo gallery. The total run time of the interior decoration of rooms on the first floor of a country house, and all the extra work was 30 days.

5 bad habits for the skin: the opinion of the body doctor Elena Malysheva

Some habits create problems for the skin, worsen its appearance and condition. Small adjustments ...

Read More

I fed the Hosts on the advice of a neighbor last year and got a lush plant. This year I will do the same

I fed the Hosts on the advice of a neighbor last year and got a lush plant. This year I will do the same

Hosta is not the rarest plant that can be found on the site. It is considered quite unpretentious...

Read More

Should you buy a robot vacuum cleaner?

Should you buy a robot vacuum cleaner?

Robot vacuum cleaner - our future or money down the drain? | ZekezakThe modern world is changing ...

Read More

Instagram story viewer