Laying of communications under the base-plate
After dumping a pillow under the base-plate, it was necessary to build it all the necessary communications. Namely, drains, IPA-pipe for laying in them underground water pipes and electric cable. So I decided to start a small tube to supply air for the furnace and boiler furnace. Not
At the beginning I will give a list of the materials already purchased and paid work in the 2018 season.
Here it is taken into account the income from the sale of the grid roll residues to the fence, and even drill TISE pine seedlings.
Sewage pipes - Only for external objects, red. Is a list of the text will not be - I hope in the screenshot seen everything. Let me explain two entries:
- IPA-pipe diameter 63mm - for input of water and the electric cable. Then water pipes pushes inside. Diameter with a large margin, enough even to 2 internal metal pipes, electrical wiring to the pump wells and the heating cable.
- IPA-pipe diameter 32mm - air supply. If they do not need or will not be effective, then they can always pour concrete or zapenit. Made in any case, what would the oven does not suck the air out of the room, and if the boiler is not enough oxygen in the furnace at a sealed door.
He brought all his car. HDPE-tube - at the trunk, fixing straps.
The drawing of the project. He did himself. Details in the previous article.
Communications are marked in red. In the upper left corner - tube output for kitchen waste. The right - the toilet on the ground floor, a sewer pipe, according to the scheme below - will be another vertical pipe from the second floor. The right vertical line - enter the water supply. In the lower right corner - to enter the underground cable.
According to the project, has marked places sewage inputs and outputs HDPE-pipes. I drove to these places armature segments. I spaced trenches and dug them into the pillow. Digs given slope, about 2-3 cm per meter.
Collecting sewage, laying in a trench connected pipes one by one. Whatever the pipe easier inserted into one another, conventional gum smeared hand cream. A connection point recorded reinforced tape.
Connecting pipes is at right angle is not recommended. At this point, the obstruction may occur. I acquired the bends 45 degrees - to establish two in those places where the pipe should rotate 90 degrees. The result was a smooth turn. In the photo below it shows.
Having laid the entire sewer system of pipes checked their slope meter level. To do this, one end tied bar, 2 cm. When you put the level of the pipe, it should show the horizon.
Sewerage system with sewage pipes that water would escape freely, did not create seething because the vacuum effect. Trench with sewage brought outside of the foundation. In all the pipes inserted plugs.
I checked as water flows. To do this on each side poured buckets of water on the floor.
HDPE pipe deep do not fit. At the ends put scraps of plastic bottles and shook his scotch.
Once again, check the slope and position of pipe O sewers and dug trenches.
Bury much faster. In places where the muffled sewerage and HDPE-pipes extend beyond the basement - Insert wooden pegs. Rebar did not drive because it is traumatic about it will constantly stumble, because it is not visible, especially at dusk.
As such, the left cushion ulezhatsya for a while until I will make permanent formwork. Rains, it will thicken even better cushion. But before installing the formwork will still ramming vibronogoy.
Further, according to the plans it had to cut it out of plywood and build molds for casting slabs of permanent formwork. I have it planned immediately with a decorative coating "Washed concrete."
Read more: Pouring boards with a decorative surface "Washed Concrete" for permanent formwork foundation