An estimate and photo report from the construction site of a house made of aerated concrete on a monolithic insulated slab with a grillage. Part 1 (foundation).
Let's start with the project and the dimensions of the house:
Foundation device:
- Foundation pit construction
- Geotextile membrane device
- Sand bed filling device
- Compaction of the sand layer with a vibrating plate
- The device for filling a layer of crushed stone with a fraction of 20x40 mm
- Formwork external and internal (under the ribs of the foundation)
- Insulation device for the basement slab with extruded polystyrene foam 100 mm
- Installation of a waterproofing layer technical film 200 micron
- Reinforcement of the foundation slab with a double reinforcing mesh with a cell of 200x200 mm with the installation of the upper mesh on the "frog" frames and reinforcement of the grillage around the perimeter with a frame of 4 longitudinal rods connected with clamps with a pitch of 400 mm (reinforcement АIII 12 mm, АI 6 mm)
- Foundation concreting device from a concrete pump, layer thickness 250 mm
- Concrete mix vibrating device
Foundation construction estimate
Implementation (photo report):
In the next article, there will be a calculation of the masonry of the walls and the device of a monolithic floor between the 1st and 2nd floors.