How to connect the gas to a private home

click fraud protection

FORUMHOUSE users are already familiar with the article, which tells about features of the heating system and water supply country house. Therefore, our website readers are well aware that at the moment natural gas is one of the most cost-effective fuels. A boiler that runs on it, different maximum level of automation, which provides comfortable accommodation in a private country house.

Despite all the benefits promised by summing up the gas, the main obstacle on the way to the "blue fuel" - is the high cost of gas to the house connection. Depending on the region, it can be 500 thousand. rubles and larger amounts. And many novice developers just do not know where the cottage gasification process begins.

Therefore, in order to bring to the house of the blue fuel in the first place, you should be familiar with the new rules, on which the gas connection to a private home. So, carrying the gas connection, Mosoblgaz guided by a new regulation.

Terms of connecting homes to the gas

Victoria Grebennik (Deputy Head of technological connection and services of SUE "MOSOBLGAZ"):
instagram viewer
- On March 1, 2014, entered into force on the decision of the Russian Federation № 1314 of the Government. One of the key changes was that the performer of works on grid connection associated with the gasification of any objects, is now a gas distribution Organization (GRO).

Previously, the developer had to independently engage in all the activities connected to the gas to the house from obtaining specifications before agreeing to a gas pipeline through the lands of different owners and the registration of all relations. According to the new decree, all issues related to the accession to the gas network to the applicants' land plots boundaries, dare GRO. That is, if the user wants to connect the gas, it is necessary to contact the Gorgaz, the regional gas companies (in the Moscow region - in Mosoblgaz). To surrender all the necessary documents and sign a contract to join the gas network, which given the work carried GRO gasification facility, the amount for the services provided and the period performance. Contractor hereunder is GRO.

Today bring gas from the point of view of the legislation has become more difficult. The existing order is different from the pre-existing primarily to the fact that the technical conditions for which can be carried out the design and construction ceased to exist as an independent document. They exist within the application to the contract of the connection. Gas connection in 2017 provides that the technical specifications that can be obtained in 14 days, are preliminary and only talk about the possibility of gasification. Bring the gas can, but not to build or design can not be in the framework of the new requirements.

Under the new requirements, request a preliminary TU forwarded to the GRO mandatory should only those consumers whose MCHRG (maximum hourly flow rate) of more than 300 cu.m / h.
Under the new requirements, request a preliminary TU forwarded to the GRO mandatory should only those consumers whose MCHRG (maximum hourly flow rate) of more than 300 cu.m / h.

What is the cost of gas connection

The main issue of concern to the applicants at the stage of deciding on the gasification of their homes - it's how much it costs to connect gas. Process connection Gas has a number of conditions determine the value. It comes from those activities that are necessary to carry out the gasification facility. For convenience, these activities are divided into 3 categories.

The main categories of the merging of capital construction

Victoria Grebennik:
 Categorization due to the use of three approaches to the formation of a connection fee.

The first category include private households, gas equipment which is designed for the consumption of gas is not more than 5 m³ / h, and subjects small business, whose fuel consumption for technological equipment connected objects does not exceed 15 cu.m / h. This category includes private home area to 300 square meters. m., and small objects communal household sector.

There is also a restriction on activities, conduct which is necessary for the gasification: the distance from the source. Gas to gas-using equipment is not more than 200 m, the pressure of the gas in the gas supply source - not more than 0.3 MPa. Only-The pipeline is to be built without the device points gas reduction. From all of these factors will depend on how much it costs gasification.

Gas connection region in the Moscow

Fixed gas supply price for the first category of objects is set by the regulator in the Moscow region in the amount of 50 thousand. rubles for private houses, in which the gas flow rate does not exceed 5 cubic meters. meters per hour. Connecting the gas in the region take into account the fuel consumption of all the equipment, including the one to which this point of the gas supply has been connected previously. Provided that the distance from the gas-powered equipment (boilers, stoves) to the nearest gas distribution network ( design working pressure of not more than 0.3 MPa), measured in a straight line to the connection point is not more than 200 meters. Events for tehpodklyucheniyu suggest this service as only the construction of pipes, pipelines inputs without reducing device points.

The second category are the objects of capital construction, for which you want to join the construction of gas distribution pipelines and / or reducing the device points; the stated amount of power exceeds the normalized volume of the first category, the pressure in the source gas of 0.6 MPa, and the like

Such objects include large private houses, etc. Summing up the gas to the house is by a standardized tariff rates. connecting the gas rate is calculated according to the method approved by the Federal Tariff and approved authority executive authority in the field of state regulation of the REC (Regional Energy Commission) in the subject, which employs the organization.

The third category are the objects of capital construction, acquisition of which is carried out on an individual project. The final determination of the cost, which is made on the basis of design and estimate documentation, which has been examined, and the final price set on each object individually executive authority in the field of state regulation in the subject in which this works organization.

Signs of this category are any objects with MCHRG more than 500 m³ / h, as well as facilities for connection requiring the passage of the lands lesfonda, marshes 3 degrees, in rocky grounds, through water barriers and any obstacles requiring the execution of works by GNB (horizontally directed drilling).

Thus, the order of the gas supply in the framework of the rules has several levels of state control to determine the cost of technological connection to the gas network.

How to calculate the maximum hourly consumption

This issue is of concern to many developers. Despite the fact that the 5 m³ / h enough for the majority of private homes, a preliminary calculation of the maximum time of gas flow can be carried out according to the following formula:

B = qh103 / Nh1,163h8000
 Where

V - gas flow equipment, m3 / h;

q - heat output of the equipment, kW;

N - efficiency factor of the equipment; typically - 90-92%;

8000 - net calorific value of natural gas, kcal / m3.

To this figure must be added all the other devices that consume natural gas in the home.

Averaged, power-burner stoves with a gas oven takes up to 10 kW. The calculation is the same as the calculation of the boiler, but without taking efficiency. Hence: 10 / 1.163 / 8 = 1.1 cu.m / h.
Averaged, power-burner stoves with a gas oven takes up to 10 kW. The calculation is the same as the calculation of the boiler, but without taking efficiency. Hence: 10 / 1.163 / 8 = 1.1 cu.m / h.
Brother Fox (User FORUMHOUSE ):
- an area of ​​100 square meters for heating homes. m required boiler output of 10 kW. Such boiler uses the average 1.2 cu.m / gas / h.

The sequence of steps to connect

Connecting the natural gas is carried out, if the technical capabilities of the gas distribution network (IAG) enable connection of new consumers, without prejudice to existing subscribers. In this case the overall gasification action algorithm includes the following steps:

  • Obtaining preliminary specifications.

In cases where the maximum hourly fuel consumption does not exceed 300 cubic meters / hour, applicants may contact the IAG for the conclusion of the connection contract without obtaining the preliminary technical conditions.

  • Application for connection and conclude with IAG of grid connection contract.

Required documents:

  • An application containing the applicant's details (passport), contact details, name and address of the location of an attached object, nature of gas consumption, the timing of the design and construction of the facility, MCHRG, number and date of the preliminary specifications, if such issued;
  • Documents confirming the ownership of the land;
  • Calculation of maximum hourly gas flow (not required if MCHRG least 5 cubic meters / hr);
  • Situation plan with reference to the territory of the municipality.

In the case of submission of all required information and documents, GRO within 30 days prepares and transmits to the applicant grid connection agreements, signed with his hand. After signing the contract the applicant and provide it to the GRO, according to the terms of the connection contract, in due time taking steps to grid connection.

And the event to the land border are made GRO, and events for the design, construction inside portion and mounting VDGO (house gas equipment) carried the applicant.

  • The implementation of measures within the area of ​​the applicant is carried out by the conclusion of contract. Design, construction and installation work on the gasification inside the area of ​​the applicant can carry out not only Gorgaz, regional gas companies, but also other construction companies, SROs are authorized (permission to carry out the relevant works) for the design, construction and installation works on the basis of the prisoner with the applicant agreement.
  • After the implementation of measures within the area the applicant sends to the customer service department IAG statement on verification of technical conditions. To the possibility of the gas supply has been implemented, and the service is provided to you properly, you must Contents: The act of acceptance of the completed construction and Act delineation of ownership and operational responsibility.
  • Conclude a contract with GRO fuel supply and maintenance of the pipeline and gas equipment.
  • GDO with an arrival of the primary starter gas.
  • Contents Act on technological connection.

On FORUMHOUSE you get access to the full FAQ gasification, Learn about the actual practice of Gas in the house under the new rulesand about the optimum number natural gas, which is recommended to ask for the house and personal experience to connect natural gas under the new rules.

Discuss the article and read other materials devoted to country life you can on the websiteFORUMHOUSE.

Subscribe to the channel so as not to miss the next release!

Facades for boxes on shkantah using homemade filler router.

Facades for boxes on shkantah using homemade filler router.

About the filler homemade Frazier I wrote earlier. here here You can see a device of this device,...

Read More

Scientists for the first time in history managed to obtain a Wigner crystal, consisting only of electrons

Scientists for the first time in history managed to obtain a Wigner crystal, consisting only of electrons

For the first time in history, engineers at ETH Zurich managed to obtain a real crystal, which co...

Read More

Vibrating screed from the rule and an old vibration pump with your own hands

Vibrating screed from the rule and an old vibration pump with your own hands

To smooth out concrete when pouring a monolithic floor, I decided on an experiment - I made a vib...

Read More

Instagram story viewer