Building a house for 3 weeks: foundation

click fraud protection

The foundation - the foundation of any construction, on the correct choice of its design depend not only the durability of the building, but also the cost of construction and its time frame

And we continue to talk about building a house for 3 weeks.

Take part in our competition and win domokomplekta! Take part in a competition.

The first phase of construction - the foundation. As we have said, project we have provided the foundation of bored piles. This type of foundation is virtually universal and suitable for all kinds of soil, the only difference is the length of the pile. In order to understand what must be the number of piles, you need to know three parameters:

  • bearing capacity of the soil in your yard;
  • estimated weight of your house with a view of the snow and the operational load;
  • putative pile diameter.

But just before the start of foundation work necessary to perform the construction site layout, so to speak, to make the contours of a house under construction on nature.

marking

Location of the house on the site is regulated in the first place, building codes and regulations. So, the main rule - to ensure the distance from the walls of the house to the fence not less than three meters. If the slope of the roof or overhang gables serve more than 0.5 m, the distance to the fence must be greater than this value.

instagram viewer

The very location of the house is recommended in view of the compass, each wall glass area and species characteristics. So, in our house, in the living room are scheduled panoramic windows, so it would be logical to place the house so as to provide a good image species.

Then we proceed to markup.

Marking the foundation is carried out by a conventional roulette. The contours of the house brought to the ground with the obligatory control of the diagonals. The working part of the project contains piles layout, a total of 15.

piling

As piles we used PVC sewer pipe outer diameter of 160 mm and 2,000 mm in length. To install using benzobura drilled holes with a diameter greater than the diameter of the pile - is perhaps one of the few processes which can not cope alone. The wells are to be drilled below the frost line. Traditional benzobura screw length of 700 mm, therefore for a further extension of the screw, we took 1000 mm. Thus, the depth of all the holes we made 1.7 meters.

Further, the bottom of each well is filled several shovel and thoroughly compacted crushed rock. Then, as the supporting heel poured into wells 2-3 shovels concrete pipe socket and set down.

To make pipes strictly vertical position and the provisional fixing between the ground and the pipe wall of the hole is filled also little debris. After aligning the tubes in two planes in each pile must be lowered by three reinforcement rod 10 mm in diameter.

The next step - pouring pile. We used to do this with the addition of samomesny concrete rubble. The total volume required for the concrete foundation is about 0.6 cubic meters, such amount can be easily manufactured alone as via mixer and manually.

Further work on the installation of the foundation raft foundation can be made no earlier than 3 days, when the concrete attains about 70% grade strength, said period may be delayed in case of unfavorable weather conditions.

After concrete hardening using gidrourovnya or laser leveling on all piles must be applied to the upper design marks and cut them into one level.

Grillage

Before the actual installation of the grillage we made harness pile board 45 * 145 mm, laid flat. Board fastened to the piles using concrete fasteners. Before mounting on the head part of each pile laid waterproofing folded in half to form a piece of roofing felt.

The presence of the strapping board, firstly, grillage facilitates installation, and secondly, this board is a support for the lag. According to the SNIP, any wooden surface, at a distance of less than 25 cm from the ground must be antiseptic, we the distance from the ground to the strapping board got about 30 cm, so we decided to play it safe and treat it antiseptic.

After that, for the protection of expanded polystyrene from rodents, we are using stepplera recorded on a binding metal grid board.

Standard on the raft foundation under the brick house on a pile foundation structure of the board allowed. However, the calculation of the estimated load allowed us to reduce the number of boards to 2. For the raft foundation, we used 145 mm wide planks, whipped each other nails.

In the future, between the bars of the grillage we assemble the joists and put the heater, but it will tell the next time.

In addition, in the next section will describe the details of the device frame walls of our house.

Subscribe to the channel and learn how the construction will develop. Become a member FORUMHOUSE and access to the mass of valuable resources!

For many, the "dew point in aerated concrete" is the worst thing. Is there a real threat (otherwise my house is still unfinished)?

Some clever and incomprehensible words sometimes seem more real. Maybe that's why all the talk an...

Read More

A small overload and what a "bad" floor looks like: a collection of repair and construction humor

A small overload and what a "bad" floor looks like: a collection of repair and construction humor

Is he also from Suicide Squad?Is he also from Suicide Squad?We were again told forced "kovikuly" ...

Read More

Instagram story viewer