A-frame in two months. Foundation
Foundation for easy triangular houses from SIP
Of course, we would like it to cost less, but the fakir was drunk and the focus was not successful: it was calculated that the house is light, and the most watery soils. The neighbors all hate the most moving, moving, this kapets as not wanted.
UWB would be fine, but too expensive. The cost of UWB would add transportation costs - the city of Miass, Chelyabinsk region. Very difficult. In the end, we decided to agree with the builders, and to make a concrete slab.
Concrete slab came at a cost of 300 thousand. It's all work and materials. Plate size - 11250 × 8000 mm, the house - 10000 × 8000 mm.
Excavation was carried out on almost 2 m, paved land on top of him was made by dumping of rubble and this pillow already made plate. Reinforced slabs, as now, many say, is not quite true reinforcement is done, but we learned about it at the stage of issuing the builders claim.
At this stage, the first time we have questioned the mathematical abilities of the builders. They did not have the concrete they poured in two stages, but on the same day and different compositions.
The first was on the cool color, almost no crack, the second is covered with cracks, lyt of a gray-yellow in color.
We are terribly angry. But all builders, including those not related to our saying we alarmist, it's milk, and other things. All agreed on one thing - our builders have decided not to cover it with foil, and that it was their mistake.
Cracks top filled "special compound"... As it turned out, it was nivelirka.