Fill piles TISE. The foundation for a bath for 15,000 rubles.
After I drilled all the holes for piles - it was already the end of July. Then began the most comfortable weather for construction without heat. Although rain frequency increased. Time for the construction of at least walls and roof bath was very small. I is not much frightened - beams can be laid in winter. But still wanted to finish his plan to the snow and at a comfortable weather with temperatures above zero.
Ordered delivery of six cubic meters of sand and gravel (ASG) for mixing concrete. Interfered in the proportions: 4 PLG buckets, bucket 1 cement, water bucket 1. Water added when more, when less, depending on the moisture of gravel. The total cost at the end of the article, in the table.
Where from and where to draw water? After the well was not. I bought two plastic barrels of 90-liter drums:
They are freely placed in the trunk of my minivan Nissan Tino.
Water took in different places: in the majority of time in the lake (dam) near the village. Muzhichkino or springs at p. Kacha in n. Emelyanovo.
I bought 12 mm diameter rebar and binding wire. Acquired on the basis of metal. He sawed his own in the same grinder on the dates along the length of the segments, and moved to his car. Service on Metal cutting on costs 30 rub. / Res.
The volume, the number of building materials and their cost for this phase I will point out just at the end.
Each pile is planned to install three rod reinforcement. Their pre-bound binding wire that would get the bulk triangle with sides about 10 cm.
According to the technique described by the manufacturer of the drill TISE, pouring piles must be performed in the "shirt" of the roofing material. In order to frost heave it slid on roofing felt and could not catch the pile and push it.
Acquired the first one, and then two more rolls. Because it makes this "jacket" and at the same time the formwork of the pile, which is located above ground. Done as follows: drill lying on the ground. Cutting the necessary segment of the roofing material, they obvorachival cup borax and countersigned book stapler (long), which remained from the previous project. Next, taking an ordinary tape and obvorachival this "shirt" continuous coating. It turns out that tape to attach great roofing felt and the strength of the concrete could not break him with his pressure on the ground.
Many do like this - set wooden formwork, sprinkle sand this place:
But my method of scotch is quite cope with the task. Neither "Shirt" is not broken, and the pile is not deteriorated. It was more difficult vertically to expose the pile at the bottom of the structure where there is a terrace. There were obtained pile height of about 0.7m. "Shirts" fixed the nails to the ground (which would not have failed at the bottom of the pile). The height of the "shirts" installed height pegs around which previously each peg has been tested gidrourovnya to all piling field to bring in one horizontal plane.
The installation process "shirts" and filling looked like this:
Immediately after pouring piles in yet uncured concrete inserted pin. They were needed for what would attract lower crown carcass baths to the foundation. The total area of bearing a small log house, log cabin is light, whatever he flew to pile field - decided to do everything safely.
Just do not need to pour concrete pile from the outside for its stability as shown in the left photo. There is a risk that in this concrete frost heave can squeeze the pile.
Just poured piles underneath the stove plate, leaving them protruding from the reinforcement rods (for cords with stove). Stove was obtained for the project hanging, resting on piles:
This is achieved as follows. Burying clay already uploaded and scored pile durability under the stove to their upper level. Obustraivalis formwork reinforced with two layers of reinforcement those residues that are left on the piles. He poured concrete in ratio of 4 to 1. Then he removed the formwork and removed all the soil from under the shovel plate. It could be done and thinner, but made with a stock.
List for the purchase of materials and the cost of all necessary to fill the pile foundation:
As you can see, its value at the time was a little over 15 thousand. rub. In today's prices, it would be probably twice as expensive. Because cement went up exactly to 2010. almost twice.
Tools and water tanks - still are not are consumable items. Boer TISE I sold a few years later almost the same price, the cost back on him.
Strip foundation did not consider his options, but it would cost many times more expensive (subject to board on the formwork and concrete delivery). It is also at times be more cost and screw piles.
Drawing attention to the cost of the foundation piles TISE poured under its structure my relatives: an uncle and brother.
Read more: Purchase of timber for the bath and Search Assistant. Tips
Read from the beginning:Why I decided to build a house?
Subscribe per channel, introducing it in the browser bookmarks. There is a lot of information.